Asbestos Removal Delays Completion Of Putnam Bridge By 1 Month

Consultation

Asbestos Removal Delays Completion Of Putnam Bridge By 1 MonthHartford CourantThe project was set back about a month from its original May 2015 completition date when asbestos was discovered in a conduit running along the frame that had to be removed, said DOT spokesman Kevin Nursick. Construction on the 56-year-old bridge, …and more »

Posted by Hartford Courant